Supreme Court tells creditors to record reasons, protect homebuyers in builder insolvency

On 15 January 2026, a Supreme Court bench of Justices J.B. Pardiwala and R. Mahadevan ruled in Elegna Co-op Housing and Commercial Society Ltd. v. Edelweiss Asset Reconstruction Company Ltd. (2026 INSC 58) that the Committee of Creditors (CoC) running a builder’s insolvency must record written reasons for any extraordinary or non-routine decision. The court also issued three binding directions aimed at protecting homebuyers whose projects end up under the Insolvency and Bankruptcy Code (IBC).

The case in brief

The dispute concerned Takshashila Heights India Pvt Ltd, which, according to the judgment, borrowed ₹70 crore in 2018 from ECL Finance to build a residential-cum-commercial project called “Takshashila Elegna”. The loans were later assigned to Edelweiss Asset Reconstruction Company, which filed a Section 7 insolvency petition. The NCLT Ahmedabad bench rejected it, but the NCLAT ordered admission in July 2025 and refused to hear the project’s housing society. The Supreme Court upheld the admission and agreed that the society had no standing to intervene.

As Bar & Bench reported, the bench held that a society or Resident Welfare Association is “neither a creditor nor an authorised representative of allottees” and that homebuyer hardship cannot stop insolvency once a financial default is established.

What the court ordered the CoC to do

The judgment says the commercial wisdom of the CoC remains “paramount” and is not ordinarily open to judicial review, but that the “width of powers vested in the CoC carries with it a corresponding duty of responsibility”. It then directed that:

  • The Information Memorandum must mandatorily disclose comprehensive and complete details of all allottees.
  • If the CoC finds it not viable to approve handover of possession under Regulation 4E of the CIRP Regulations, it must record cogent and specific reasons in writing.
  • Any CoC recommendation for liquidation must carry a reasoned justification in writing, showing that all viable alternatives were considered.
  • These directions operate prospectively and apply immediately.

Where homebuyers stand under the IBC

The bench restated the protections already available to buyers. Allottees who are still waiting for their homes are recognised financial creditors who can file claims and take part in CoC decisions through authorised representatives. Buyers already in possession stand outside the insolvency estate, and Regulation 4E allows handover of possession with 66% CoC approval. The court also referred to its 2025 ruling in Mansi Brar Fernandes, which described RERA as the primary forum for homebuyer grievances and the IBC as a forum of last resort meant to revive viable projects.

What it means for buyers in stalled projects

The ruling does not give individual buyers or their associations a new right to block an insolvency petition. What it changes is accountability inside the process: a CoC that refuses to hand over completed units, or that votes to liquidate a developer, now has to explain that choice in writing. Those written reasons create a record that affected allottees can examine and, where the Code allows, challenge before the tribunal.

For buyers, the practical steps are to file claims on time with the resolution professional, stay in touch with the authorised representative chosen for their class, and check that their details appear in the Information Memorandum. Anyone weighing a fresh purchase can reduce exposure to under-construction risk by comparing ready homes, for example properties for sale in Noida or homes for sale in Gurgaon, and by checking a project’s RERA registration and litigation history. More explainers are on the RealtyMandi blog.